PECB ISO-9001-Lead-Auditor Question Answer
You work for an organisation, 'ABC', which provides packaged food to the public. You are asked to lead a team (you as the leader and two other
auditors) to audit an external provider, 'XYZ', which provides packaging materials to your organisation. It is 4 pm, and the audit is dlose to an end;
you are having an internal meeting with the team to decide what will be presented to the auditee during the Closing meeting. The Closing meeting
was scheduled for 5 pm.
'XYZ' has two manufacturing lines: M1 is a clean room for primary packaging materials (i.e. will be in direct contact with the food), and M2 is for
secondary materials (i.e. will not be in direct contact with food).
Auditor 1 audited the two manufacturing lines.
You: "What findings would you report?"
Auditor 1: "I have one issue. Earlier today in the morning I saw some secondary material stocked in the clean room. I would propose raising a
nonconformity."
You: "How would you write the nonconformity?"
Auditor 1: "In the clean room, there was a pallet with secondary materials."
What additional information would you add to this text to complete the nonconformity report? Select six.