GSC Ltd is a manufacturer of car parts.

GSC Ltd is a manufacturer of car parts. To accommodate growing demands of electric cars, the company is developing a new component which requires different type of steel. The project team estimates that the component will be ready for production in 1.5 years. Until then, they need to keep the production busy.

After checking the inventory records, the production team sees that the company has 3 months of stock. The lead time for each batch is two months. Which of the following should be a priority ac-tion of the company?

A.

Create new specification to new supplier

B.

Standardise the specification

C.

Create new specification to current supplier

D.

Make a call-off order to current supplier

CIPS L4M2 Summary

  • Vendor: CIPS
  • Product: L4M2
  • Update on: Jan 29, 2026
  • Questions: 303
Price: $52.5  $149.99
Buy Now L4M2 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method