James Hunter has received a price increase request from a supplier with its justification. The supplier has requested the price increase because there has been an increase in staff sickness absence. James has reviewed the original contract and found a buyer provision for 'risk for additional resource.' This is the first year the supplier has experienced a resource issue. What should James do?