Over the life of a product, which of the following would be considered non-value-adding costs?

Over the life of a product, which of the following would be considered non-value-adding costs?

    Rework costs

    Production costs

    Maintenance costs

    Waste disposal costs

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4