CIPS L4M3 Question Answer
A manufacturing company signed a contract with a raw material supplier. The contract includes a clause on liquidated damages in case of late delivery. Purchaser was obliged to pay after 30 days from delivery. Eventually raw material was delivered 1 week later than initial plan due to supplier’s slow production process. There is no defect in the delivered batch. Which of the following can be claimed by the manufacturing company?