Infra Constructions receive a contract for construction of a building, and following terms were agreed...

Infra Constructions receive a contract for construction of a building, and following terms were agreed upon. "The entire cost of the project will be reimbursed to Infra Constructions (estimated cost of the project being $ 25 million). The profits will be 20% of the entire cost of a project subject to a max of $ 5 million." This arrangement is an example of...?

A.

Incentive pricing arrangement

B.

Gain-share/pain-share arrangment

C.

Cost-plus pricing arrangement

D.

Fixed-pricing arrangement

CIPS L4M3 Summary

  • Vendor: CIPS
  • Product: L4M3
  • Update on: Jul 30, 2025
  • Questions: 196
Price: $52.5  $149.99
Buy Now L4M3 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method