CIPS L4M5 Question Answer
XYZ Ltd needs to purchase a bundle of IT products from suppliers. The procurement manager requests details of costs regarding designing and managing those products. After receiving reports from suppliers, she realises that they have charged up to a 1,095% mark-up on IT products. In order to ensure value for money, which of the following should be a priority pricing arrangement of the procurement manager in the negotiation with these IT suppliers?