CIPS L5M8 Question Answer
Ali is a Project Manager at a large retail organisation within the UK. He has created a project timeline and allocated a budget. However, two months into the project the UK declares a national lockdown due to an unknown virus sweeping the nation. What type of complexity is this known as?