XYZ is a large construction organization running five different projects.

XYZ is a large construction organization running five different projects. Each project has a specific type of contract and pricing mechanism.

Your task is to match the correct type of contract and pricing mechanism to each project.

Projects and Descriptions

    Project 1

      Description: Construction of an apartment block, where XYZ is responsible for both design and construction. Upon completion, ownership is transferred to the client.

      Pricing Mechanism: Based on past experience of similar projects.

Project 2

    Description: Facilities management for a 6-year period after construction. The budget is constantly adjusted due to industry volatility.

    Pricing Mechanism: Budget changes continuously over time.

Project 3

    Description: XYZ was involved from an early stage, but does not bear the design risk. The budget resets at the start of each new accounting period.

    Pricing Mechanism: The budget is refreshed periodically.

Project 4

    Description: XYZ is responsible for certain parts of the design and build, while another company handles other aspects. XYZ is paid upon milestone completion.

    Pricing Mechanism: Payment is milestone-based.

Project 5

    Description: Construction of a new toll bridge which will be operated by XYZ for the first 6 years post-construction. The pricing includes costs of raw materials, labor, and a profit margin.

    Pricing Mechanism: Costs plus profit.

CIPS L6M5 Summary

  • Vendor: CIPS
  • Product: L6M5
  • Update on: Jul 30, 2025
  • Questions: 83
Price: $52.5  $149.99
Buy Now L6M5 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method