A Photovoltaic (PV) system was installed on a 35,000 ft2 (3 252 m2) project.

A Photovoltaic (PV) system was installed on a 35,000 ft2 (3 252 m2) project. What actions need to take place in order to meet compliance for Energy and Atmosphere Prerequisite, Fundamental Commissioning (Cx) and Verification?

A.

No action is necessary as the PV system is not required to be commissioned

B.

The PV system installer should commission his own installations and share the results with the project owner

C.

The Cx agent for the project must conduct or oversee the Cx of the PV system

D.

The building's mechanical engineer should commission his own installations and share the results with the project owner

USGBC LEED-AP-BD+C Summary

  • Vendor: USGBC
  • Product: LEED-AP-BD+C
  • Update on: Aug 2, 2025
  • Questions: 337
Price: $52.5  $149.99
Buy Now LEED-AP-BD+C PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method