A company needs to be alerted when the calculated planned cost of a bill of...

A company needs to be alerted when the calculated planned cost of a bill of materials (BOM) product is older than 30 days.

You need to configure the number of days validation in the system.

Where should you specify the number of days?

Select only one answer.

A.

Cost price model

B.

Stop explosion

C.

Inventory and warehouse management parameters

D.

BOM calculation groups

E.

Released product

Microsoft MB-330 Summary

  • Vendor: Microsoft
  • Product: MB-330
  • Update on: Oct 28, 2025
  • Questions: 404
Price: $52.5  $149.99
Buy Now MB-330 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method