A manufacturing company uses master planning in Dynamics 365 Supply Chain Management.

A manufacturing company uses master planning in Dynamics 365 Supply Chain Management.

The production planner increases the lead time of an item. On the next master planning output the planner receives a cancel action message on existing purchase orders. The message includes a suggested earlier date for the planned purchase orders.

The demand for the item has not changed since the original purchase order was placed. Dynamic negative days is not used.

You need to resolve the issue.

What should you do?

A.

Increase positive days.

B.

Decrease positive flays.

C.

Decrease negative days to be less than the item lead time.

D.

Increase negative days to be greater than the item lead time.

Microsoft MB-335 Summary

  • Vendor: Microsoft
  • Product: MB-335
  • Update on: Dec 23, 2025
  • Questions: 209
Price: $52.5  $149.99
Buy Now MB-335 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method