PeopleCert MSP-Practitioner Question Answer
The programme is in the ‘deliver the capabilities’ process in Tranche 3. Engineering staff have been installing the new water meters. As a result, fewer staff than planned have attended the first few training courses, delivered as part of the Training Project. If this trend continues, realization of the reduced costs could be delayed. The programme manager has asked the CEngO to schedule this routine work so that the engineers can attend training courses in the future.
Which theme is MOST relevant to this situation, and why?