The programme is in the ‘deliver the capabilities’ process in Tranche 3.

The programme is in the ‘deliver the capabilities’ process in Tranche 3. Engineering staff have been installing the new water meters. As a result, fewer staff than planned have attended the first few training courses, delivered as part of the Training Project. If this trend continues, realization of the reduced costs could be delayed. The programme manager has asked the CEngO to schedule this routine work so that the engineers can attend training courses in the future.

Which theme is MOST relevant to this situation, and why?

A.

Decisions, because the programme manager is responding to possible delays to the training courses affecting programme benefits

B.

Decisions, because the problem with the delayed training courses is causing a delay to delivery of the programme benefits

C.

Justification, because the delays to the training courses could impact how quickly the reduced costs are realized

D.

Justification, because further delays to the training courses will start to impact programme costs, affecting the business case

PeopleCert MSP-Practitioner Summary

  • Vendor: PeopleCert
  • Product: MSP-Practitioner
  • Update on: Feb 21, 2026
  • Questions: 133
Price: $52.5  $149.99
Buy Now MSP-Practitioner PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method