200 units each of components F, G and H are required next period.

200 units each of components F, G and H are required next period.

All three components are made by skilled labour of which only 4,000 hours are available.

An external supplier is able to supply any requirements of the components.

No inventories are held.

Data for the three components are as follows:

In order to minimise cost, how many units of component H should be purchased from the external supplier?

A.

None

B.

80

C.

120

D.

200

CIMA P1 Summary

  • Vendor: CIMA
  • Product: P1
  • Update on: Jul 29, 2025
  • Questions: 260
Price: $52.5  $149.99
Buy Now P1 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method