CIMA P1 Question Answer
Forecast sales demand of product W next period is 6,800 units. Product W requires 5 kg of material Y, seven hours of skilled labour and six hours of semi-skilled labour.
Availability of resources for next period is forecast as follows:
No inventories are held.
What is the principal budget factor for next period?