CIMA P2 Question Answer
A cost centre manager's performance is monitored based on a comparison of actual and budgeted cost. A summary performance report for the latest period is shown below.
The actual costs include:
*$28,000 for allocated head office costs.
*$18,000 payment for a rental agreement entered into by the cost centre manager two years ago.
*$34,000 for depreciation.
What is the cost centre manager's controllable actual cost for the period?
Give your answer to the nearest $000.