A cost centre manager's performance is monitored based on a comparison of actual and budgeted...

A cost centre manager's performance is monitored based on a comparison of actual and budgeted cost. A summary performance report for the latest period is shown below.

The actual costs include:

*$28,000 for allocated head office costs.

*$18,000 payment for a rental agreement entered into by the cost centre manager two years ago.

*$34,000 for depreciation.

What is the cost centre manager's controllable actual cost for the period?

Give your answer to the nearest $000.

CIMA P2 Summary

  • Vendor: CIMA
  • Product: P2
  • Update on: Jul 29, 2025
  • Questions: 202
Price: $52.5  $149.99
Buy Now P2 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method