The performance report for the production manager of a company for the last month included...

The performance report for the production manager of a company for the last month included the following.

1,000 direct labor hours were worked at a basic rate of pay of $10 per hour. 200 of these hours were worked during overtime for which a 30% overtime premium was paid. 80 of these overtime hours were to fulfill a customer order that had originally been planned for manufacture next month. The sales manager had agreed to bring forward the delivery of this order at the request of the customer. The remaining overtime hours were due to unexpected inefficiency of the workforce; this has been traced to poor supervision by a junior manager.

Material costs included the following:

    $5,300 of material A. Material A is a commodity and, due to changes on the global market, the actual unit cost of this material for last month was 6% higher than had been expected

    $5,250 of material B. The usage of material B last month was 5% higher than it should have been due to faulty workmanship on the production line.

What is the total value of the above costs that was controllable by the production manager?

A.

$20,610

B.

$19,810

C.

$20,910

D.

$20,360

CIMA P2 Summary

  • Vendor: CIMA
  • Product: P2
  • Update on: Jul 29, 2025
  • Questions: 202
Price: $52.5  $149.99
Buy Now P2 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method