Which THREE of the following are true with regard to managing the changeover from an...

Which THREE of the following are true with regard to managing the changeover from an old to a new computer system?

A.

Pilot changeover moves the simplest part of the business to the new system first

B.

Parallel running involves keeping the old system running normally until certain data retention criteria are met or confidence is gained, while the new system deals with the new workload Data input is usually earned out on both systems

C.

All methods of changeover carry high risk and it is the preparation consideration of data compatibility and data cleansing before the changeover which has the biggest impact on the smoothness of the transition

D.

Phased changeover moves individual portions of the business to the new system one at a time

E.

Direct changeover, or big bang, is only used when the systems are significantly different such that comparing the outputs of the two systems is largely irrelevant

F.

Phased changeover is the safest and slowest method of changeover

CIMA P3 Summary

  • Vendor: CIMA
  • Product: P3
  • Update on: Jul 29, 2025
  • Questions: 339
Price: $52.5  $149.99
Buy Now P3 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method