Which should be documented in a Blueprint?

Which should be documented in a Blueprint?

A.

Benefit Profiles for individual benefits to be delivered by the P3O

B.

Transition plans for the implementation of business change into business as usual

C.

Need for Business Cases for mission-critical programmes to be reported to the Portfolio Board

D.

Actual Highlight Reports issued by individual projects