Assume the organization's strategy has undergone a significant change, and as a result the mix...

Assume the organization's strategy has undergone a significant change, and as a result the mix of components in the portfolio also will change. As the portfolio manager, you need to update your charter in order to reflect:

A.

The new 'to be' vision

B.

Interdependencies between the new components

C.

Risk tolerances

D.

Key stakeholders