Assume you are working in a division in your country's Department of Interior.

Assume you are working in a division in your country's Department of Interior. The Department is set up in Bureaus, and your work falls within Natural Resources. Your division is the Water Resource Division. You are responsible as the portfolio manager for the work in this Division. As you work on the portfolio for the upcoming year, you point out to the members of the Portfolio Review Committee that:

A.

The projects in the portfolio have interdependencies between them

B.

Your portfolio reflects your Division's objectives

C.

Each program and project in the portfolio have related objectives

D.

Your portfolio addresses different strategies than those in other parts of the Department

PMI PfMP Summary

  • Vendor: PMI
  • Product: PfMP
  • Update on: Jul 30, 2025
  • Questions: 495
Price: $52.5  $149.99
Buy Now PfMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method