A company CEO issues a mandate to automate a new-client onboarding process to replace manual...

A company CEO issues a mandate to automate a new-client onboarding process to replace manual and paper-based procedures. After the program sponsor and program manager obtain formal acceptance of the program charter, what should be done next?

A.

Deploy a team to develop the program management plan.

B.

Develop estimates for scope, resources, and cost.

C.

Identify the program management components, and develop the resource management plan.

D.

Review and update the benefits management plan and link it to program outcomes.

PMI PgMP Summary

  • Vendor: PMI
  • Product: PgMP
  • Update on: Jul 25, 2025
  • Questions: 452
Price: $52.5  $149.99
Buy Now PgMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method