Robert's program is slipping on its schedule and management has asked that Robert find a...

Robert's program is slipping on its schedule and management has asked that Robert find a method to compress the duration of the program. What approach could Robert take that would not dramatically add risks to program if he added labor to the effort-driven activities within the program?

A.

Lead time

B.

Crashing

C.

Lag time

D.

Fast tracking