You are the program manager of the JNH Program.

You are the program manager of the JNH Program. Tom, a project manager in your program, has just completed his project and is ready to officially close his project. You agree that Tom's project is completed. What role do you play in Tom's project closure?

A.

You must ensure that the project sponsor closes the project.

B.

You must ensure that that the projects within the program have been closed at the project level.

C.

You must close the project before operations closes the project.

D.

You must ensure that the program management team closes the project for the project manager.

PMI PgMP Summary

  • Vendor: PMI
  • Product: PgMP
  • Update on: Jul 25, 2025
  • Questions: 452
Price: $52.5  $149.99
Buy Now PgMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method