Your program has 121 stakeholders that you'll need to communicate with.

Your program has 121 stakeholders that you'll need to communicate with. Your communications management plan defines how the communication should happen, what should be communicated, and the expected modality of the communications. You'll also need which one of the following as an input to the information distribution process in your program?

A.

Change requests

B.

Earned value management results

C.

Stakeholder analysis plan

D.

Performance reports

PMI PgMP Summary

  • Vendor: PMI
  • Product: PgMP
  • Update on: Jul 25, 2025
  • Questions: 452
Price: $52.5  $149.99
Buy Now PgMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method