Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmasmnth

A stakeholder expresses a need not known to the project manager.

A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

A.

Plan Stakeholder Management

B.

Identify Stakeholders

C.

Manage Stakeholder Engagement

D.

Control Stakeholder Engagement

PMI PMI-001 Summary

  • Vendor: PMI
  • Product: PMI-001
  • Update on: Jul 25, 2025
  • Questions: 918
Price: $52.5  $149.99
Buy Now PMI-001 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method