Fast tracking is a schedule compression technique used to shorten the project schedule without changing...

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?

A.

The risk of achieving the shortened project time is increased.

B.

The critical path will have positive total float.

C.

Contingency reserves are released for redeployment by the project manager.

D.

Duration buffers are added to maintain a focus on planned activity durations.

PMI PMI-001 Summary

  • Vendor: PMI
  • Product: PMI-001
  • Update on: Jul 25, 2025
  • Questions: 918
Price: $52.5  $149.99
Buy Now PMI-001 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method