Which of the following methods is a technique used to predict project duration by analyzing...

Which of the following methods is a technique used to predict project duration by analyzing which sequence of activities has the least amount of scheduling flexibility?

A.

Dependency diagramming

B.

PERT

C.

Critical Path

D.

Grant chart