The "To Complete Performance Index" (TCPI) is calculated by:

The "To Complete Performance Index" (TCPI) is calculated by:

A.

Subtracting the actual costs to date from the estimate at completion

B.

Dividing the budgeted cost of the remaining work by the difference between the estimate at completion and actual costs to date

C.

Multiplying the estimate at completion by the cumulative cost performance index

D.

Adding the estimate at completion to the actual costs to date and multiplying by the cumulative cost performance index

PMI PMI-002 Summary

  • Vendor: PMI
  • Product: PMI-002
  • Update on: Jul 25, 2025
  • Questions: 748
Price: $52.5  $149.99
Buy Now PMI-002 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method