You are project manager of a project.

You are project manager of a project. A scope change requested by a client after acceptance of the design has a potential impact on several components of the project. What do you do?

A.

Convince the client to postpone the change.

B.

Estimate the impact to the cost and schedule and the approval before proceeding.

C.

Make the change if it is critical, regardless of its cost and impact, and in form the change control boar