You are the controller on your project.

You are the controller on your project. Your project manager has requested that you provide him with a forecast of project costs for the next 12 months. He needs this information to determine if the budget should be increased or decreased on this major construction project. In addition to the usual information sources, which of the following should you also consider?

A.

Cost estimates from similar projects

B.

The WBS

C.

Long-range weather forecasts

D.

Existing change requests

PMI PMI-002 Summary

  • Vendor: PMI
  • Product: PMI-002
  • Update on: Jul 25, 2025
  • Questions: 748
Price: $52.5  $149.99
Buy Now PMI-002 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method