Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence...

Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?

A.

Monitor and Control Risks

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis