PMI PMI-100 Question Answer
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000
PMI PMI-100 Summary
- Vendor: PMI
- Product: PMI-100
- Update on: Jul 25, 2025
- Questions: 704
PMI PMI-100 Question Answer
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000