A product owner with experience in a predictive approach wants the team to develop very...

A product owner with experience in a predictive approach wants the team to develop very detailed schedules and cost estimates for the next 10 sprints. What should the Scrum Master do?

A.

Suggest the product owner start by focusing on the next 2 sprints instead of 10

B.

Spend the first few sprints to develop detailed schedules and budgets

C.

Invite the product owner to the retrospective to explain the team's approach to schedule and budget

D.

Explain that detailed project schedules and budgets are not artifacts in agile projects

PMI PMI-200 Summary

  • Vendor: PMI
  • Product: PMI-200
  • Update on: Jul 25, 2025
  • Questions: 482
Price: $52.5  $149.99
Buy Now PMI-200 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method