A project team has been working on five data source integrations.

A project team has been working on five data source integrations. They have allocated one tester for each data source. One of the testers is on emergency leave for personal reasons, so the project

deliverables could not be completed on time.

How should the project team improve during their retrospective for future implementations?

A.

Use the scrum or team board and daily scrum meetings to track and manage issues and optimize deliverables.

B.

Encourage team members to become general specialists to reduce bottlenecks and create a cross-functional team.

C.

Empower teams and encourage emerging leadership to produce effective solutions to manage complexity.

D.

Define the roles of the individual or group and define the what, how, why, when, and where to do each task.

PMI PMI-200 Summary

  • Vendor: PMI
  • Product: PMI-200
  • Update on: Jul 25, 2025
  • Questions: 482
Price: $52.5  $149.99
Buy Now PMI-200 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method