An agile project has three more iterations before the release.

An agile project has three more iterations before the release. There is a lot of report functionality to be created and defects to be cleared. During a daily scrum, a team member suggests a timebox spike to find a more efficient way to deliver reports.

What should the project leader do?

A.

Encourage the team to self-organize and determine how to best complete their existing work and this spike.

B.

Encourage the team to complete their just existing work since the team velocity indicates they are already struggling to meet the release goal.

C.

Direct the team to defer the spike until the next release and add the action on the backlog for prioritization.

D.

Direct the team to work on the spike immediately given the importance of reporting functionality to complete the iteration.

PMI PMI-200 Summary

  • Vendor: PMI
  • Product: PMI-200
  • Update on: Jul 25, 2025
  • Questions: 482
Price: $52.5  $149.99
Buy Now PMI-200 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method