Based on the burndown chart, what is the iteration's status?

Based on the burndown chart, what is the iteration's status?

A.

It trended ahead of schedule and completed everything on time

B.

It took more time than expected and had to be lengthened.

C.

It trended behind schedule and did not complete everything on time

D.

It took less time than expected and had to be shortened.