Midway through a sprint, the scrum master identifies that reassigning a certain task could help...

Midway through a sprint, the scrum master identifies that reassigning a certain task could help the team meet its sprint goals What should the scrum master do next?

A.

Alert the team that sprint goals might not be met and create an alternative plan

B.

Obtain team buy-in to perform modifications to the sprint backlog.

C.

Have the sprint proceed as planned

D.

Ask the team to decide if the task should be reassigned

PMI PMI-200 Summary

  • Vendor: PMI
  • Product: PMI-200
  • Update on: Aug 7, 2025
  • Questions: 482
Price: $52.5  $149.99
Buy Now PMI-200 PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method