A senior manager has asked an agile team to ensure that the data for the...

A senior manager has asked an agile team to ensure that the data for the burndown charts are updated in real-time. However, the team is not comfortable with this approach as they think this is not productive.

What should the scrum master do?

A.

Ask the product owner to manage and share the metrics with appropriate stakeholders.

B.

Meet with requestors to agree and align on reporting requirements.

C.

Deny the request and explain the team's stance to the stakeholders.

D.

Work with the team to create the metrics requested by the stakeholders.

PMI PMI-ACP Summary

  • Vendor: PMI
  • Product: PMI-ACP
  • Update on: Jul 25, 2025
  • Questions: 476
Price: $52.5  $149.99
Buy Now PMI-ACP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method