Analyzing theburndown chart, we see:
Points Planned(gray squares): decreasing steadily from 50 to 0 over 10 days (ideal burn).
Points Completed(gray triangles):plateau between days 3–6, lagging significantly behind planned completion.
This indicates that theteam is behind schedule, and unless they accelerate, they mayfail to complete all committed work.
According to thePMI Agile Practice Guide (Section 5.4: Burndown Charts)andMike Griffiths’ PMI-ACP Exam Prep Book (Chapter 6: Monitoring Progress), such divergence between the ideal and actual burn lines indicates that the iteration isat risk.
Option Ais correct: the iteration isin jeopardydue to lack of progress mid-sprint.
Option Bis incorrect—scope removal would show a downward shift in planned points.
Option Cis false—the team isbehind, not ahead.
Option Dis misleading—velocity appears inconsistent (e.g., plateau from day 3–6).