Halloween Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmasmnth

During project inception, an agile practitioner engages the stakeholder to ensure alignment on the project's...

During project inception, an agile practitioner engages the stakeholder to ensure alignment on the project's strategy and vision. The stakeholder asks for detailed requirements, design, and delivery plans.

What should the agile practitioner do?

A.

Provide all information requested by the stakeholder

B.

Set expectations regarding the appropriate level of details requested during this stage

C.

Inform the stakeholder that no detailed documents are provided using agile practices

D.

Ask the team to supply the information to the stakeholder

PMI PMI-ACP Summary

  • Vendor: PMI
  • Product: PMI-ACP
  • Update on: Oct 31, 2025
  • Questions: 476
Price: $52.5  $149.99
Buy Now PMI-ACP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method