Midway through a project, the product owner learns from the sponsor that a major component,...

Midway through a project, the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project.

What should the product owner do next?

A.

Obtain approval from the change control board to discontinue the component

B.

Ask the team to continue developing the component

C.

Ask the team to discontinue developing the component

D.

Request the sponsor ' s formal approval to discontinue the component

PMI PMI-ACP Summary

  • Vendor: PMI
  • Product: PMI-ACP
  • Update on: May 6, 2026
  • Questions: 481
Price: $52.5  $149.99
Buy Now PMI-ACP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method