Stakeholders are unhappy because they have not been consulted on a user interface (UI) for...

Stakeholders are unhappy because they have not been consulted on a user interface (UI) for a project that will have a significant impact on end users once it is launched.

How should this situation be handled?

A.

The Agile team should engage stakeholders regarding the proposed designs and ensure that sufficient engagement occurs throughout the project in an adaptive way.

B.

The Agile practitioner should inform the stakeholders that the UI has already been approved by the project team and sponsor, so the team is committed to staying the course.

C.

All stakeholders should go through the approved project charter and business requirements document to reduce the number of late changes or requests.

D.

The stakeholders should contact the project sponsor to get the project halted until new requirements are agreed upon.

PMI PMI-ACP Summary

  • Vendor: PMI
  • Product: PMI-ACP
  • Update on: Jul 25, 2025
  • Questions: 476
Price: $52.5  $149.99
Buy Now PMI-ACP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method