The product owner is present at the sprint review meeting and states that an estimation for the end of the project must be shared with the company’s steering committee. The scrum master declares that the team reached an average velocity of 40 story points per sprint, considering a biweekly iteration. The team members predict that there are 240 story points remaining.
What is the estimated project conclusion?
PMI PMI-ACP Summary
- Vendor: PMI
- Product: PMI-ACP
- Update on: Oct 31, 2025
- Questions: 476


 Velocity = 40 story points per sprint
Velocity = 40 story points per sprint Remaining Work = 240 story points
Remaining Work = 240 story points Sprint Duration = 2 weeks
Sprint Duration = 2 weeks

 
 