A stakeholder has rejected a project's deliverable because it does not meet the original business...

A stakeholder has rejected a project's deliverable because it does not meet the original business need. It is further determined that the deliverable does not meet the requirements identified in the baseline.

What is the best approach to resolve this issue?

A.

Meet with the customer and apologize for misunderstanding the business's need.

B.

Suggest re-estimating the requirement and following the change control process.

C.

Provide the stakeholder with a copy of the approved requirements baseline and move forward without making a change.

D.

Require development resources to work overtime to modify the deliverable to satisfy the stakeholder.

PMI PMI-PBA Summary

  • Vendor: PMI
  • Product: PMI-PBA
  • Update on: Jul 29, 2025
  • Questions: 200
Price: $52.5  $149.99
Buy Now PMI-PBA PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method