A stakeholder requests to add new critical requirements the day before the scheduled baseline requirements...

A stakeholder requests to add new critical requirements the day before the scheduled baseline requirements approval meeting. The stakeholder insists that these requirements must be taken into account despite time and budget constraints.

What is the most effective way to manage this situation?

A.

Discuss the change with stakeholders during the baseline approval meeting and ask them to approve the new baseline.

B.

Ask for more resources to manage this change and justify these additional resources with the value the change will give to

the company.

C.

Share the new requirements with all stakeholders and ask them to submit their comments before the meeting.

D.

Postpone the baseline approval meeting, analyze the impact, and schedule a new meeting to discuss dependencies and

priorities with stakeholders.

PMI PMI-PBA Summary

  • Vendor: PMI
  • Product: PMI-PBA
  • Update on: Jul 29, 2025
  • Questions: 200
Price: $52.5  $149.99
Buy Now PMI-PBA PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method