PMI PMI-PMOCP Question Answer
A PMO professional is acting as the PMO leader temporarily in a well-established and mature PMO unit. In this role, a PMO professional receives an escalation from the portfolio manager that a new business stakeholder's activity is overlapping with key portfolio management functions.
What should the PMO professional do to resolve this issue?