A project is in progress when the product team requests a change to the scope.

A project is in progress when the product team requests a change to the scope. The team indicates that this is a minimal change and should not create any problems.

What should the risk manager do next?

A.

Update the work breakdown structure (WBS).

B.

Analyze any potential impact.

C.

Escalate the issue to management.

D.

Add a new risk to the risk register.