A project lihat was in the execution phase for the last six months was put on hold and was eventually cancelled after numerous scope related challenges. It was decided to re-plan the scope and divide the project into multiple projects to have better insight into end objectives. As part of the project start up. the project manager is developing the risk planning for the project.

What three artifacts should the project manager consult or review during this process? (Choose three.)

A.

Project contracts

B.

Lessons learned registers from analogous projects

C.

Risk register

D.

Risk management plan

E.

Code of regulations

PMI PMI-RMP Summary

  • Vendor: PMI
  • Product: PMI-RMP
  • Update on: Jul 25, 2025
  • Questions: 264
Price: $52.5  $149.99
Buy Now PMI-RMP PDF + Testing Engine Pack

Payments We Accept

Your purchase with ExamsVCE is safe and fast. Your products will be available for immediate download after your payment has been received.
The ExamsVCE website is protected by 256-bit SSL from McAfee, the leader in online security.

examsvce payment method