PMI PMI-RMP Question Answer
A project team has completed plan risk response activities and has identified three critical risk response plans to major risk events. The responses have been monitored and implemented, with one of the responses presenting the two secondary risks.
What should the risk manager do next?
PMI PMI-RMP Summary
- Vendor: PMI
- Product: PMI-RMP
- Update on: Jul 25, 2025
- Questions: 264